Single-pole and double-pole MCB selection begins with the conductors that the circuit must switch and protect. A familiar pole label is not enough: a single-phase circuit may be line-to-neutral or line-to-line, and a two-pole product may have a different protected-Disposición de los postes from another two-pole product.

A practical way to frame the pole decision
Draw the complete circuit first, including the source, neutral, protective conductor, shared neutrals and the intended isolation point. Then record whether each pole is switched, protected, or both. The MCB selection range can be reviewed after those inputs are fixed, not before.
Which conductors must the device disconnect?
A single-pole MCB may suit a line conductor where the applicable installation rules permit that arrangement. A double-pole device may be required where line and neutral must open together, but the selected model must document how the neutral pole is treated. Shared or borrowed neutrals are a common reason to stop and redraw the circuit.
What does a single-pole MCB actually cover?
One pole does not automatically describe the entire circuit’s isolation or fault behaviour. Verify the rated voltage, breaking capacity, protected pole and the installation rule for the circuit topology. A nominally single-phase supply is not always a line-to-neutral supply.

Why should 1P+N be reviewed separately from 2P?
1P+N commonly indicates line-and-neutral switching with overcurrent protection on the line pole, while a 2P device can have another protection arrangement. Treat the labels as a prompt to inspect the wiring diagram and markings, not as interchangeable product names.
When does a double-pole MCB become the better review route?
Consider it when simultaneous disconnection is required by the design or local rules, when the supply arrangement makes both conductors part of the isolation boundary, or when the selected product’s documented ratings match that duty. Pole count does not by itself increase breaking capacity.
How should the comparison appear on the panel schedule?
List the circuit topology, pole configuration, protected poles, AC or DC duty, rated voltage, breaking capacity, trip curve and neutral arrangement as separate fields. This makes supplier responses comparable and exposes missing information before the bill of materials is released.
Which product pages can support the shortlist?
For a model-level check, review the interruptor automático en miniatura CQB2-63 page and compare its published configuration with the panel drawing. Related MCB options should be treated as separate model reviews.
When is pole count not enough for final selection?
Stop the comparison and return to the responsible designer when the project needs discrimination, local-code interpretation, a DC application, shared neutrals or model-specific approval. IEC 60898-1 y IEC 60947-2 have different scopes, so the applicable standard must be identified rather than assumed.
For a double-pole MCB selection, the final schedule should show the actual line and neutral arrangement, protected-pole designation and the evidence used to approve the device.
That record is also useful when a later service change introduces a shared neutral or a different supply topology. The installer can see which assumptions were part of the original approval instead of treating the pole label as a universal rule.
It also gives the panel reviewer a clear way to reject a nominally similar device when its terminal marking, neutral treatment or permitted voltage does not match the approved circuit.
Preguntas frecuentes
¿Cuál es la diferencia básica entre un MCB 1P y un 2P?
Un MCB de 1P tiene un polo para el conductor asignado. Un MCB de 2P tiene dos polos vinculados mecánicamente que se abren juntos. La documentación del producto seleccionado aún debe confirmar la función y la disposición de protección de cada polo.
¿Es 1P+N lo mismo que 2P?
No. Una etiqueta 1P+N se asocia comúnmente con la conmutación de fase y neutro con protección contra sobrecorriente en el polo de fase, mientras que un dispositivo 2P puede tener una disposición de polos protegidos diferente. Confirme tanto el diagrama de cableado como las marcas del producto antes de tratarlos como alternativas.
¿Una etiqueta 2P demuestra que ambos polos están protegidos?
No. El recuento de polos por sí solo no establece cómo se protege cada polo. Solicite la hoja de datos y la información de cableado del modelo seleccionado, luego compárelos con el requisito del circuito.
¿Se puede utilizar un interruptor automático magnetotérmico (MCB) de CA en un circuito de CC?
Solo cuando el dispositivo exacto esté explícitamente clasificado y documentado para el servicio de CC previsto. La norma IEC 60898-2 aborda requisitos adicionales para interruptores automáticos de CA/CC unipolares y bipolares elegibles, pero no hace que todos los interruptores automáticos en miniatura (MCB) de CA sean adecuados para CC.
¿Qué normas debe revisar un constructor de tableros para una solicitud de interruptor automático en miniatura (MCB)?
Empiece por la norma y la regla de instalación nombradas en los documentos del proyecto. IEC 60898-1 cubre los interruptores automáticos de CA para uso doméstico e instalaciones similares dentro de su ámbito, mientras que IEC 60947-2 es un contexto de norma de interruptores automáticos de baja tensión para personas instruidas o cualificadas. El requisito del proyecto y los documentos del modelo seleccionado determinan la base final.
¿Qué debe incluirse en una solicitud de cotización (RFQ) para un MCB?
Incluya el diagrama unifilar, la disposición de la alimentación y de los circuitos, los conductores que se van a conectar, la expectativa de polos protegidos, la corriente de CA o CC, la norma aplicable, la evidencia requerida del modelo seleccionado, las restricciones del panel y cualquier solicitud de marca o embalaje.
¿Cuándo no es suficiente esta guía para la selección final?
No es suficiente cuando el proyecto requiere coordinación final, interpretación de códigos locales, orientación sobre trabajo en vivo o una aprobación específica del modelo. Esas decisiones requieren la información real del circuito y de la carga, las normas locales y la documentación del producto seleccionado.